Engineering Bid Results

The following engineering project bid results are as-opened and read into the record at the City of Elkhart Board of Public Works meetings.  Unless otherwise noted, these results have not been analyzed for errors and are not the official results presented to the Board with award recommendation.  Official results are not typically available until the following Board of Works meeting, and can be obtained by contacting the Engineering Department at EngineeringBidRequests@coei.org

BOW Meeting Date 9/19/17, official results – awarded same day

Rinehart Place Sewer & Water Extension – Bid #17-26

  • Niblock Excavating, Inc. $239,491.25 – awarded contract
  • HRP Construction, Inc. - $264,400.00
  • C&E Excavating, Inc. - $270,684.25
  • Indiana Earth, Inc. - $303,029.21
  • Rieth-Riley Construction Co., Inc. - $351,540.00

Lamar Court Water Extension – Bid #17-28

  • HRP Construction, Inc. - $239,000.00 – awarded contract
  • Rieth-Riley Construction Co., Inc. - $351,895.00
  • Indiana Earth, Inc. - $372,441.00
  • C&E Excavating, Inc. - $389,980.00

Van Buren St Water Main Extension – Bid #17-29

  • C&E Excavating, Inc. - $123,731.00 – awarded contract
  • HRP Construction, Inc. - $130,000.00
  • Niblock Excavating, Inc. - $133,187.50
  • Rieth-Riley Construction Co., Inc. - $138,870.00
  • Indiana Earth, Inc. - $173,676.00

BOW Meeting Date 3/21/17, official results - awarded same day

Morton & Hovey Storm Sewer - Bid #17-05

  • Niblock Excavating, Inc. - $97,092.50 - awarded contract
  • John Boettcher Sewer & Excavating - $117,307.13
  • Rieth-Riley Construction Co., Inc. - $129,705.00
  • HRP Construction, Inc. - $139,110.00

BOW Meeting Date 2/21/17, official results available 3/7/17

Magnolia Water Main Extension - Bid #17-06

  • C&E Excavating, Inc. - $213,797.60
  • Niblock Excavating, Inc. - $219,000.00
  • Rieth-Riley Construction Co., Inc. - $227,739.35
  • John Boettcher Sewer & Excavating - $227,856.27
  • Beer & Slabaugh, Inc. - $240,807.75
  • Selge Construction Co., Inc. - $252,417.75

 Cottage Court Water Extension - Bid #17-07

  • John Boettcher Sewer & Excavating - $277,561.70
  • Rieth-Riley Construction Co., Inc. - $283,591.50
  • Niblock Excavating, Inc. - $305,850.00
  • C&E Excavating, Inc. - $306,716.50
  • Beer & Slabaugh, Inc. - $330,868.75
  • Selge Construction Co., Inc. - $417,018.25

BOW Meeting Date 2/7/17, official results available 2/21/17

SR 120 & Suburuban Water Extension - Bid #17-01

  • C&E Excavating, Inc. - $111,686.75
  • Niblock Excavating, Inc. - $119,089.75
  • Indiana Earth, Inc. - $123,011.05
  • John Boettcher Sewer & Excavating - $125,941.36
  • Rieth-Riley Construction Co., Inc. - $147,304.00
  • Selge Construction Co., Inc. - $164,929.25
  • HRP Construction, Inc. - $206,856.00